This is your logbook. Insert here all relevant information regarding the evolution of your project

Weekly Report

1st Week Report

  • The group arranged a meeting in order to get familiar.
  • Started assigning tasks to different team members.
  • Discussed a few ideas about marketing plans.

2nd Week Report

  • The first official meeting with the supervisors took place
  • Task allocation and Gantt Chart was done
  • Searching for components and materials already in progress
  • Discussion about suggested ideas and advice which appeared during the 1st official meeting

3rd Week Report

Things that happened this week:

  • Research on modules and materials continued
  • First flowchart was created
  • First draft of a logo was created
  • First draft of leaflet was created
  • Ethical code concerning our teamwork was set up and signed by teammembers
  • Tried to find an appropriate market for the final product

4th Week Report

Things that happened this week:

  • Leaflet was handed in
  • Marketing plan was handed in
  • List of material was handed in
  • Spoke to client

5th Week Report

During our Eastern holiday week we:

  • Started the state of the art
  • Started to design webpage
  • Started to modify a scrum document for project management, so that we can use one in the future.

6th Week Report

Things that happened this week:

  • We started to insert more info to the report sub-page on the wiki
  • We finished the scrum excel file and are now able to use it for project management.
  • We updated the gantt chart so that it matched the scrum file.
  • We started to modify the existing marketing plan for the interim report.
  • We started to write the sustainability and ethics part for the interim report

7th Week Report

Things that happened this week:

  • Leaflet was updated according to Anas' comments.
  • All separate documents were compiled into a interim report document.
  • Presentation for interim report was created.
  • All deliverables were uploaded to the wiki.

8th Week Report

Things that happened this week:

  • Team prepared for the interim report presentation.
  • Presentation was held.
  • Feedback was received.

9th Week Report

Things that happened this week:

  • We started to modify the report accoding to the comments that we received.

10th Week Report

Things that happened this week:

  • We updated the marketing plan with an action prgramme and budget. We are still waiting for feedback from Andreia Gama.
  • Schematics were updated.

Meetings

1st Meeting (2013-03-01)

Agenda:

  1. Presentation
  2. Modus operandi
  3. Project proposal
  4. Electronic Logbook

Minute:

  1. A team familiarized with the Wiki Page
  2. Project topic was chosen
  3. The first discussion about the project took place
  4. A list of suggested questions for the first official meeting with supervisors was created

2nd Meeting (2013-03-07)

Agenda:

  1. Presentation of team
  2. Communication/Communication module
  3. Power supply
  4. Data storage
  5. Weight
  6. Suppliers
  7. Radiation/ radiation control
  8. Materials

Minute:

It was decided that we should:

  • Create a list of devices/modules that meet the requirements
  • Insert all attributes from devices into a list for easy comparison (power consumption, price and dimensions have to be taken into consideration)
  • Check allowed levels of radiation, temperature etc. for pets as well as for humans
  • Get Pro-form invoice from chosen supplier. Get VAT from Benedita
  • Develop web interface in Linux. App for Android
  • Figure out how to minimize the power consumption
  • Define detailed scope of product

Other suggestions:

  • Product as “clip-on” or collar (the matter of weight)
  • Client's name is José Barros Oliveira

3rd Meeting (2013-03-14)

Agenda:

  1. Considerations about prototype
  2. Battery/battery charging module
  3. Battery step-up regulator
  4. Using the GSM/GPRS module
  5. Using the GPS module
  6. Standalone chip(PIC/AVR) vs arduino
  7. Suppliers restrictions
  8. Mobile Website vs Mobile App

Minute:

It was decided that we should:

  • Create a “Top to bottom” agenda list next time.
  • Create a Block diagram and add contents to it.
  • Add logging to flowchart
  • Choose if update interval should be fixed or adaptive.
  • Investigate in FSK modules. Might need external antennas.
  • Define final test requirements.
  • Check with G7electronica 800 102 037 if they can agree upon paying after receiving materials
  • Create a list as Manuel suggested.

Other suggestions/comments:

  • Modes: Sleep mode when no activity. Wake up when activity resumes.
  • Suppliers: Inmotion, Farnel

4th Meeting (2013-03-21)

Agenda:

  1. Tracking system integration
  2. Q2686 Module(Antenna, Mechanical Integration, Programming)
  3. XM0110 Module(Antenna, Mechanical Integration)
  4. GSM/GPRS to webserver

Minute:

  • General considerations about the the Q2686 and XM0110 modules
  • A transparent connection must be established between the communication module and the server

5th Meeting (2013-04-05)

Agenda:

  1. Interim report(What to expect, guidelines, suggestions)
  2. Interim Presentation
  3. Building the pet tracker

Minute:

  • Supervisors explained how the report and the presentation should be structured.
  • They also showed us where to find templates for the required documents.

6th Meeting (2013-04-11)

Agenda:

  1. General considerations about the report

Minute:

  • Supervisors commented on some of the things for our report.
  • Meeting was short due to lack of topics on the agenda.

7th "Meeting" (2013-04-11)

Agenda:

  • Interim presentation

Minute:

  • Presentation
  • Discussion

8th Meeting (2013-04-26)

Agenda:

  1. Power Supply design - evaluation of the current design
  2. Programming the Arduino Pro Mini

Minute:

It was decided that we should:

  • check the feedback from other professors about the report
  • think about the switching regulators
  • look for some regulators modules - there exist better suggestions than we found
  • think about users' manual
  • prepare more detailed signal schemating and drawings

9th Meeting (2013-05-02)

Agenda:

  1. Status update on the components.
  2. What happens if we are not allowed to buy the components.
  3. Tasks to fulfill for the next days/weeks (what to do until we get the components?).

Minutes:

It was decided that we should:

  • specify as much as possible all schematics
  • keep on working with the web interface
  • start programming soon

10th Meeting (2013-05-09)

Agenda:

  1. Some more pictures

Minutes:

  • Rethink power diagram. Use more simple solution.

11th Meeting (2013-05-16)

Agenda:

Minutes:

It was decided that we should:

  • think about a current booster in our diagram
  • meet with Mr. Joao Fransisco Silva to discuss few things connected with plastic container
  • consider different types of container in Marketing Plan

12th Meeting (2013-05-23)

Agenda:

  • TBA

Minutes:

  • TBA

Activities

Please register here all project activities

Start End Task Description Who
1.3.2013 3.3.2013 Choose project - All
1.3.2013 7.3.2013 Assign tasks to team members - All
10.3.2013 10.3.2013 Hand in task allocation chart All
15.3.2013 18.3.2013 Create leaflet - Anton & Ola
1.3.2013 20.3.2013 Research modules - Artur
1.3.2013 21.3.2013 Make list of materials - All
19.3.2013 19.3.2013 Spread questionnaire on social medias - All
20.3.2013 21.3.2013 Researching the modules specifications - Artur
21.3.2013 21.3.2013 Create Marketing Plan - Anton & Ola
24.3.2013 25.3.2013 Update the list of materials - Artur
4.4.2013 4.4.2013 Create a workplan (product and sprint backlog) - Anton
4.4.2013 5.4.2013 Updated gantt chart - Anton
5.4.2013 6.4.2013 Start defining use cases - Marti
8.4.2013 10.4.2013 Updated sustainability and ethics part - Ola
8.4.2013 12.4.2013 Interim report - All
12.4.2013 13.4.2013 Interim report revision - Anton and Artur
12.4.2013 13.4.2013 Finish smartphones market analysis - Marti
13.4.2013 14.4.2013 Start designing power diagrams - Artur
22.4.2013 22.4.2013 Create new template for final report - Artur
29.4.2013 2.5.2013 Improving the report - Artur
1.5.2013 5.5.2013 Updating Marketing Plan - Anton & Ola
5.5.2013 6.5.2013 Defining final tests - Marti
9.5.2013 9.5.2013 Power supply redesign - Artur

Material List

ProductLinkDescriptionQuantity
GPShttps://www.sparkfun.com/products/8234EM-408 with Antenna/MMCX1
Arduinohttps://www.sparkfun.com/products/11114Arduino Pro Mini 328 - 3.3V/8MHz 1
Batteryhttp://pt.rs-online.com/web/p/paquetes-de-baterias-de-litio-recargables/5306325/ENIX 3,7V 1840mAh1
GPRS/GSMhttps://www.sparkfun.com/products/10138ADH80661
GPRS/GSM Boardhttps://www.sparkfun.com/products/10497ADH8066 Breakout1
Chargerhttps://www.sparkfun.com/products/10401LiPo Charger Basic - Mini-USB1
Antenna(GSM)http://pt.rs-online.com/web/p/antenas-gsm-y-gprs/7043417/GSMMQB - Mini Quad Band Antenna1
Accelerometerhttps://www.sparkfun.com/products/10955Triple Axis Accelerometer Breakout1
Memory http://pt.rs-online.com/web/p/chips-de-memoria-eeprom/0454145/I2C EEPROM - 1Mbit1
QR Code
QR Code log (generated for current page)